Objective
This article will outline the typical lead times to be expected when placing a number port request with 8x8.
Note that all estimates provided here are guidelines only, not a guarantee of expected lead time. Our team are dedicated to making your number porting experience as quick and smooth as possible, but number porting requests involve multiple providers and can therefore be delayed by factors outside 8x8's control.
Porting to 8x8
Step One - Submit the port request via 8x8 Admin Console and you will receive a case reference in the format: C1234567.
Step Two - Varies based on location:
Canada or USA - Skip step two.
Republic of Ireland, United Kingdom or the rest of the world - You will receive an email titled Number Transfer Request, as shown below. See the required documentation in 8x8 Number Porting LOAs, for the relevant country. Once the paperwork is gathered and completed please reply to the email, or upload documents to your case via the 8x8 Support Portal.
Step Three - We will validate your request and get in touch via your case to advise if any further information is required before we can proceed.
Step Four - We will submit your port request to the current provider targeting your preferred date or, if this is unavailable, the earliest available date.
From this point the lead time for your port request will depend on the country, carrier, volume of numbers and the accuracy of the information provided on your porting documentation. For the best estimate of how long your port request will take to be completed once it has been submitted to the current provider, see below for a breakdown of the minimum lead times.
Minimum Lead Times
Below are the minimum lead times for number porting with 8x8. These estimates assume that accurate information is supplied upon submission of the port request in Admin Console & on any supporting documentation. If your port request is rejected by the current provider, based on the information supplied, then the process must be restarted and the lead time resets.
Canada | |
|---|---|
1 - 49 local Numbers | 7 business days |
50+ local Numbers | 15 business days |
Toll Free Numbers | 3 business days |
Republic of Ireland | |
|---|---|
1 - 49 Numbers | 5 business days |
50+ Numbers | 7 business days |
United Kingdom | |
|---|---|
1 number | 11 business days |
2 - 49 Numbers | 15 business days |
50 - 149 Numbers | 20 business days |
150+ Numbers | 25 business days |
United States of America | |
|---|---|
1 - 49 Local Numbers | 7 business days |
50+ Local Numbers | 15 business days |
Toll Free Numbers | 3 business days |
Rest of the World
The lead times vary significantly on a country by country basis. For most we would recommend allowing at least 20 business days. If you would like to know the typical lead time for a specific country please submit the port request and, when contacted by our number porting team, ask for more detail on the expected time frame.
Other Porting Timescales
For details on other number porting actions for which lead times apply, please see below.
Process | Scenario | Lead Time |
|---|---|---|
Cancellation | My port request is accepted but I no longer want the number to port. How much notice do I need to give to cancel the port date? | |
Date Change | My port request is accepted but the scheduled date is not suitable. How much notice do I need to give to change the port date? | |
Rejections | My port request has been rejected by the current provider. How long will my request remain open for revised information to be provided? | 5 business days |
Porting Away from 8x8
To port your 8x8 telephone numbers away to a new provider, the port request would need to be initiated via your new provider.
To establish the correct information to be included on your port request you can raise a 'CSR request' with 8x8.
To check a rejection which your new provider has received from 8x8 you can raise a 'Port Out Rejection' with 8x8.
To change the company/address details your numbers are registered to you can raise a 'Carrier Records Update' with 8x8.
See below the typical lead times for how long your Port Out case will take to be completed. Note that if multiple actions are required then multiple lead times will apply.
CSR Requests | ||
|---|---|---|
Countries Involved | Volume of Numbers | Lead Time |
Single Country | 1 - 199 numbers | 7 business days |
Single Country | 200 - 999 numbers | 10 business days |
Single Country | 1000+ numbers | 15 business days |
Multiple Countries | Any | Lead time will vary based on volume & countries involved |
Port Out Rejection | ||
Single Country | Any | 7 business days |
Multiple Countries | Any | Lead time will vary based on volume & countries involved |
Carrier Records Update | ||
Single country | 1 - 199 numbers | 7 business days |
Single country | 200 - 999 numbers | 10 business days |
Single country | 1000+ numbers | 15 business days |
Multiple Countries | Any | Lead time will vary based on volume & countries involved |